MG6103 Engineering Management Principles : Solution Essays

Question:

New Laboratory Facilities at the Technology Park

You are the Project Coordinator of the new Laboratory Facilities at the new Technology Park being built in Manukau

Project Details

Choose one project according to your area of study (Civil, Mechanical and Electrical). Use representative data and add appropriate resources (people, materials and cost).You will decide how the project will be managed. Set the project start date as Monday the 30th of October 2019 in MS project. The project must be completed in time for the opening of the second semester on the 27th of July 2020.  

Electrical:  Installation of Electrical Engineering laboratory equipment to the new Technology Park.

Broad areas to be covered:

  • Identification of equipment to be installed ( and procurement of additional lab equipment),
  • Layout and arrangement of electrical equipment in the laboratory,
  • Identification of service providers and work teams,
  • Connection of services (Electrical wiring of equipment, water, compressed air and gas),
  • Networking and calibration of equipment,
  • Commissioning of equipment.
 

Answer:

New Laboratory facilities at the Technology Park

Project set up activities

List of set up activities

Project schedule for laboratory setup

   Project initiation stage

      Selection and identification of building facilities

      Development of accurate organizational structure, responsibility allocation

      Feasibility analysis

      Selection of equipments those have to purchased

      Appointing technicians and skilled staffs

   Project planning stage

      Identification of emergency exit space

      Installing safety devices and equipments

      Designing view panel at the exit door

      Flooring

      Wall and ceiling

      Proper plumbing

      Installing fire extinguisher

   Project execution stage

      Grounding all electrical outlets

      Electrical socket outlets

   Project monitoring phase

      Cross checking three phase wiring

      Final checkup of the voltage using multimeter

      Final user acceptance testing

   Project closure

      Stakeholder signoff

      Post laboratory maintenance program

      Submission of final project document

Project constraints

Triple project constraints are considered for accomplishment of the electrical engineering laboratory equipment setup in New technology Park. The total time and budget predicted for the project are 189 days and $127,256. It is duty of the project associates and other coordinators to use play assigned role and complete the setup in assigned timeline and budget only. The start date and finish date of the project are 30th October, 2019 and 20th July, 2020. The total cost assigned for each activity are elaborated in the below tabular form.

 

Project cost

Name of the activities

costs

Project schedule for laboratory setup

$127,256.00

   Project initiation stage

$5,376.00

      Selection and identification of building facilities

$640.00

      Development of accurate organizational structure, responsibility allocation

$1,216.00

      Feasibility analysis

$1,680.00

      Selection of equipments those have to purchased

$1,120.00

      Appointing technicians and skilled staffs

$720.00

   Project planning stage

$66,440.00

      Identification of emergency exit space

$768.00

      Installing safety devices and equipments

$19,152.00

      Designing view panel at the exit door

$1,800.00

      Flooring

$4,080.00

      Wall and ceiling

$640.00

      Proper plumbing

$20,000.00

      Installing fire extinguisher

$20,000.00

   Project execution stage

$25,560.00

      Grounding all electrical outlets

$560.00

      Electrical socket outlets

$25,000.00

   Project monitoring phase

$26,600.00

      Cross checking three phase wiring

$25,000.00

      Final checkup of the voltage using multimeter

$1,120.00

      Final user acceptance testing

$480.00

   Project closure

$3,280.00

      Stakeholder signoff

$1,200.00

      Post laboratory maintenance program

$1,120.00

      Submission of final project document

$960.00

Work Breakdown Structure

 

Figure 1: Project work breakdown Structure

(Source: Created by Author)

Timeline and milestone report

Costs measured for each resource are mentioned in the below table:

WBS

Task Name

Duration

Start

Finish

0

Project schedule for laboratory setup

189 days

30/10/19

20/07/20

1

   Project initiation stage

47 days

30/10/19

02/01/20

1.1

      Selection and identification of building facilities

10 days

30/10/19

12/11/19

1.2

      Development of accurate organizational structure, responsibility allocation

12 days

13/11/19

28/11/19

1.3

      Feasibility analysis

10 days

29/11/19

12/12/19

1.4

      Selection of equipments those have to purchased

15 days

29/11/19

19/12/19

1.5

      Appointing technicians and skilled staffs

10 days

20/12/19

02/01/20

2

   Project planning stage

58 days

03/01/20

24/03/20

2.1

      Identification of emergency exit space

3 days

03/01/20

07/01/20

2.2

      Installing safety devices and equipments

12 days

08/01/20

23/01/20

2.3

      Designing view panel at the exit door

12 days

24/01/20

10/02/20

2.4

      Flooring

15 days

24/01/20

13/02/20

2.5

      Wall and ceiling

12 days

11/02/20

26/02/20

2.6

      Proper plumbing

10 days

27/02/20

11/03/20

2.7

      Installing fire extinguisher

9 days

12/03/20

24/03/20

3

   Project execution stage

22 days

25/03/20

23/04/20

3.1

      Grounding all electrical outlets

12 days

25/03/20

09/04/20

3.2

      Electrical socket outlets

10 days

10/04/20

23/04/20

4

   Project monitoring phase

41 days

24/04/20

19/06/20

4.1

      Cross checking three phase wiring

15 days

24/04/20

14/05/20

4.2

      Final checkup of the voltage using multimeter

19 days

15/05/20

10/06/20

4.3

      Final user acceptance testing

7 days

11/06/20

19/06/20

5

   Project closure

21 days

22/06/20

20/07/20

5.1

      Stakeholder signoff

5 days

22/06/20

26/06/20

5.2

      Post laboratory maintenance program

9 days

29/06/20

09/07/20

5.3

      Submission of final project document

7 days

10/07/20

20/07/20

Gantt chart with dependencies

 

Figure 2: Activity dependency

(Source: Created by Author)

Network diagram for the project

 

Figure 3: Network chart for the project

(Source: Created by Author)

After changing predecessors in some of the project development activities it is identified that the project time will get decrease from 134 days 189 days. After making changes in the dependencies or predecessors the numbers of days has been decreased but the total cost is enhanced by $164,592.

 

 

Bibliography

Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.

Conforto, E.C. and Amaral, D.C., 2016. Agile project management and stage-gate model—A hybrid framework for technology-based companies. Journal of Engineering and Technology Management, 40, pp.1-14.

Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kliuchnikova, O.V. and Pobegaylov, O.A., 2016. Rationalization of Strategic Management Principles as a Tool to Improve a Construction Company Services. Procedia Engineering, 150, pp.2168-2172.

Kontogiannis, T., Leva, M.C. and Balfe, N., 2017. Total safety management: principles, processes and methods. Safety science, 100, pp.128-142.

Marcelino-Sádaba, S., González-Jaen, L.F. and Pérez-Ezcurdia, A., 2015. Using project management as a way to sustainability. From a comprehensive review to a framework definition. Journal of cleaner production, 99, pp.1-16.

Marchewka, J.T., 2016. Information technology project management: Providing measurable organizational value. John Wiley & Sons.

Martens, M.L. and Carvalho, M.M., 2017. Key factors of sustainability in project management context: A survey exploring the project managers’ perspective. International Journal of Project Management, 35(6), pp.1084-1102.

Newton, P., 2015. Principles of Project Management. Disponível: https://www. free-management-ebooks. com/dldebk-pdf/fme-projectprinciples. pdf.

Sholarin, E.A. and Awange, J.L., 2016. Environmental Project Management: Principles, Methodology, and Processes. Springer.

Slack, N. and Brandon-Jones, A., 2018. Operations and process management: principles and practice for strategic impact. Pearson UK.

Talman, J., 2018, August. Enhancing Teamwork in Group Projects by Applying Principles of Project Management. In Innovations in Teaching & Learning Conference Proceedings (Vol. 10).

Place your order
(550 words)

Approximate price: $22

Homework help cost calculator

600 words
We'll send you the complete homework by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 customer support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • 4 hour deadline
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 300 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more
× How can I help you?