MNG00785 Project Management 2 : Solution Essays

Question:

Project Charter:

You are required to explain the theory behind a Project Charter, and to develop a Project Charter based on the scenario below. The Charter must include all the elements in Sections 3-4 to 3-5, pages 35-79 of the textbook. You must draw heavily on the theory contained in the textbook and the PMBoK. You are expected to include all the relevant Charter sections shown in the textbook, and model your tables on the relevant textbook exhibits.

There are two parts to your Charter:

  1. The first section will discuss the theory behind each element of the Charter. 
  1. The second section of the assessment is your actual project charter.

Scenario

You are the Branch Manager for an insurance company in a suburban location. The lease on your company’s offices has expired and the landlord has indicated that it will not be renewed. You have two months to vacate the premises. You have identified a possible new location in a nearby suburb and the CEO has asked you to prepare a project proposal. She has indicated that you are expected to project manage the move, and that your budget for the move is no more than $100,000. You want to accomplish the move with the minimum disruption to staff and customers, in as short as time as possible, and under budget.

The following staffing will be allocated:

CEO – sponsor Project team:

  • Branch Manager who will act as Project Manager
  • The manager of Communications and Information Technology (CIT)
  • The administration manager

As Project Manager, it is your responsibility to manage the project with the least disruption to existing staff, within budget, and within a four day window. Your company has a group of labourers who are available to assist in the project, and the CIT department will provide the Subject Matter Experts for the computer and telephone move.

The project team has agreed that the move will occur in 6 weeks time, with packing up undertaken on a Friday afternoon, removal and relocation on Saturday and Sunday, and staff to complete set up on Monday morning when they return to work in the new premises. The aim is to have as little downtime as possible. The communications and information technology team will work all weekend to ensure all equipment is operational before Monday morning.

 

Answer:

Part 1: Project Charter Elements

A project charter is defined as an overall basic plan for an upcoming project that serves as the predecessor to the full project plan and emphasizes on some of the basic but critical components of the project plan. In a project charter, there are a number of different elements that are discussed below with specific reference to literature.

Project Scope and Objectives

According to Kerzner and Kerzner (2017), project scope refers to the set of goals and the overall boundary that has to be successfully fulfilled at the end of the project. On the other hand, project objectives represent the deliverables of the project and must be defined before proceeding with the rest of the project.

Project Business Case

Project business case is defined as a set of various factors related to the project (Harrison and Lock 2017). These factors include the purpose of project, possible benefits of the project, appropriate reasoning for conducting the project and others.

Project Schedule, Milestones and Deliverables

Project schedule is the total estimated time period that is required to complete all the work in the project. The deliverables represent the work requirements of the project and milestones represent specific points within the project that reflects the end point of a particular phase or a group of work in the project (Sharp, Peters and Howard 2017). The deliverables of the project are assigned with several work packages that are required to fulfill the deliverables. These work packages are considered for developing the estimated schedule for the project.

Risk Identification

Risk identification is a customary project activity that is conducted to identify the main risks associated with the project (Crawford 2014). Identification of the risks early helps to develop appropriate mitigation plan that will be used to neutralize the impacts of the risks on the project.

 

Project Assumptions and Constraints

As per Flyvbjerg (2014), project assumptions refer to some assumptions that are made during planning the project. These assumptions are required when there are chances or possibilities of occurrence of certain impactful events that may or may not occur during the course of the project. Assumptions are also required during estimation of schedule and budget of the project. Project constraints are the factors that can hinder the progress of the project. These constraints must be identified during planning of the project so that possible modifications can be made on the project to avoid the constraints.

Estimation of Resources

Any project requires various resources for execution. Again, resources are of two types – human resource and material resource (Schwalbe 2015). Estimation of resource refers to the identification of the quantity of the resources (both human and material) that will be required for successful execution of the project.

Stakeholder Identification

For successful management of a project, it is important to identify the main stakeholders associated with the project (Mir and Pinnington 2014). Stakeholders are the personnel who have control over specific parts of the project and their duties include ensuring each of the parts are executed as per the plan.

Team Operating Principles

Any project team requires a number of operating principles that each project team member must follow throughout the course of the project (Marcelino-Sádaba et al. 2014). These operating principles must be defined before the team members are allocated with tasks for the project.

Lessons Learned

This section allows the project team members to reflect on the success of their own works and how they have learnt throughout the course of planning of the project.

Charter Closing and Signatures

This is the final section of the project charter that includes a list of signatures of all the stakeholders associated with the project (Nicholas and Steyn 2017). After the signatures are received, the project charter is officially closed and forwarded to management for verification and approval.

Project Charter for Given Project

Letter to Sponsor

To

The CEO

Barrier Reef Insurance Company

Dated: 28/03/2019

Subject: Regarding Office Relocation

Madam,

I hope you are already updated about the ending of our current lease in the office space we are using. However, I am disappointed to inform you that the owner does not want to increase the duration of the contract and has requested us to find a new office space. As a gesture of goodwill, the landlord has allowed us 2 months of time within which, we need to vacate the office premises. Accordingly, we have conducted a search for a new office space and we found a suitable one near the Kingston Suburb. We have also analyzed that we will require a budget of around $70,000 in order to complete the relocation process. I have attached the project charter with this letter and I would request you to please go through it and make a decision regarding approval of the budget that we have developed.

Thanks & Regards,

Name:

Branch Manager,

Barrier Reef Insurance Company.

Project Scope and Objectives

The main scope of the project is to relocate the insurance office to the new selected office space without affecting the daily operations of the company. The preparations of the project need to be made throughout the month and the relocation process has to be completed within a weekend so that the operations need not be stopped at any point of time.

The objectives of the project are determined using SMART technique as follows:

Specific

To relocate to new office space due to expiry of contract for the current office space

Measurable

Two months are provided for completing the relocation process and vacating the current office premises; a maximum budget of $100,000 has been proposed for the relocation process

Acceptable

The relocation process is to be completed over one weekend without interrupting regular operations at the office

Realistic

The relocation process should not incur costs exceeding $100,000

Time Based

The relocation must be completed over the weekend

Project Business Case

This project is required because the current office space cannot be further used and must be vacated within two months period. The benefit of the project is that the new office space will be rented for a long term contract and the new location will allow the company to attract new customers from a new suburb.

 

Project Schedule, Milestones and Deliverables

The main deliverable of the project is to relocate the office from one location to another. This is to be achieved by renting a new office space and relocating all the office materials including workstations, furniture and utilities.

The milestones of the project are specified as follows.

Task Name

Milestone 1: Receive Approval for Relocation

Milestone 2: Finalize Contract with New Office Space Owner

Milestone 3: Relocation Complete

Milestone 4: Sign Off

Finally, the complete schedule of the project is shown in the following table.

Task Name

Duration

Start

Finish

Project for Relocation of Insurance Office

39.5 days

Mon 4/29/19

Thu 6/13/19

   Initial Survey and Planning

17 days

Mon 4/29/19

Tue 5/21/19

      Survey Area for Selection of New Office Space

10 days

Mon 4/29/19

Fri 5/10/19

      Select a Space for Office

2 days

Mon 5/13/19

Tue 5/14/19

      Discuss Regarding Rent and Relocation Plan

3 days

Wed 5/15/19

Fri 5/17/19

      Submit Proposal to Authority

2 days

Mon 5/20/19

Tue 5/21/19

      Milestone 1: Receive Approval for Relocation

0 days

Tue 5/21/19

Tue 5/21/19

   Project Detailed Planning and Initiation

10 days

Wed 5/22/19

Tue 6/4/19

      Assign SMEs and Develop Team for Project

2 days

Wed 5/22/19

Thu 5/23/19

      Prepare Project Charter

1 day

Fri 5/24/19

Fri 5/24/19

      Estimate Budget Required for Relocation

1 day

Mon 5/27/19

Mon 5/27/19

      Estimate Overall Time Schedule for the Relocation Process

1 day

Tue 5/28/19

Tue 5/28/19

      Make Assumptions and Identify Risks for the Project

3 days

Wed 5/29/19

Fri 5/31/19

      Determine Project Constraints

2 days

Mon 6/3/19

Tue 6/4/19

      Milestone 2: Finalize Contract with New Office Space Owner

0 days

Tue 6/4/19

Tue 6/4/19

   Project Execution

7.5 days

Fri 6/7/19

Mon 6/10/19

      Packaging and Cleaning Up

34 hrs

Fri 6/7/19

Sun 6/9/19

      Loading Luggage on Relocation Truck

2 hrs

Sun 6/9/19

Sun 6/9/19

      Relocate Everything to New Office Space

2 hrs

Sun 6/9/19

Sun 6/9/19

      Setting Up and installation of Equipments and Utilities

16 hrs

Sun 6/9/19

Mon 6/10/19

      Installation of the Employees’ Workstations

6 hrs

Mon 6/10/19

Mon 6/10/19

      Milestone 3: Relocation Complete

0 hrs

Mon 6/10/19

Mon 6/10/19

   Review and Closing of Project

3 days

Tue 6/11/19

Thu 6/13/19

      Finish Payments for Previous Office

1 day

Tue 6/11/19

Tue 6/11/19

      Advance Payment to New Office Space Owner

1 day

Wed 6/12/19

Wed 6/12/19

      Review the Overall Office

1 day

Thu 6/13/19

Thu 6/13/19

      Milestone 4: Sign Off

0 days

Thu 6/13/19

Thu 6/13/19

 

 

Risk Identification

There are some risks associated with the project that are listed in the following table along with mitigation plan.

Risk Description

Mitigation Plan

During relocation, some office equipment may get damaged or broken

Ensure proper handling of the equipments and careful loading and unloading to and from the relocation truck

The relocation process may hamper daily operations of the company

The relocation process must be completed within the course of a weekend, working overtime if necessary

There might be contractual disagreements regarding the new office space

Ensure there are no disputes or disagreements left before signing the contract and relocating to the new space

Project Assumptions and Constraints

The assumptions and constraints of the project are as follows.

  • It has been assumed that maximum budget of $100,000 is sufficient for the relocation process.
  • It has been assumed that the relocation process can be successfully completed over one weekend.
  • Contractual agreements with the owner of the new office space can be a constraint as it can take a significant amount of time.
  • The office shifts pose as a significant constraint as they cannot be stopped due to relocation process.

Estimation of Resources

The following table shows the resources required (both human and material) for executing the project.

Resource Name

Type

Std. Rate

Project Manager

Work

$150.00/hr

Manager of CIT

Work

$95.00/hr

Manager of Supervision and Project Administration

Work

$115.00/hr

Subject Matter Experts

Work

$400.00/hr

Workers

Work

$350.00/hr

Transportation Costs

Material

$5,000.00

Additional Costs

Material

$1,500.00

These resources are allocated to the work packages and the overall estimated budget for the project is determined and shown in the following table.

Task Name

Resource Names

Cost

Project for Relocation of Insurance Office

 

$67,320.00 [TOTAL BUDGET]

   Initial Survey and Planning

 

$19,800.00

      Survey Area for Selection of New Office Space

Manager of Supervision and Project Administration

$9,200.00

      Select a Space for Office

Manager of Supervision and Project Administration

$1,840.00

      Discuss Regarding Rent and Relocation Plan

Manager of Supervision and Project Administration, Project Manager

$6,360.00

      Submit Proposal to Authority

Project Manager

$2,400.00

      Milestone 1: Receive Approval for Relocation

 

$0.00

   Project Detailed Planning and Initiation

 

$9,720.00

      Assign SMEs and Develop Team for Project

Manager of CIT

$1,520.00

      Prepare Project Charter

Project Manager

$1,200.00

      Estimate Budget Required for Relocation

Manager of Supervision and Project Administration

$920.00

      Estimate Overall Time Schedule for the Relocation Process

Manager of Supervision and Project Administration

$920.00

      Make Assumptions and Identify Risks for the Project

Manager of Supervision and Project Administration

$2,760.00

      Determine Project Constraints

Project Manager

$2,400.00

      Milestone 2: Finalize Contract with New Office Space Owner

 

$0.00

   Project Execution

 

$32,700.00

      Packaging and Cleaning Up

Workers

$11,900.00

      Loading Luggage on Relocation Truck

Workers

$700.00

      Relocate Everything to New Office Space

Workers, Transportation Costs[1]

$5,700.00

      Setting Up and installation of Equipments and Utilities

Workers, Subject Matter Experts

$12,000.00

      Installation of the Employees’ Workstations

Subject Matter Experts

$2,400.00

      Milestone 3: Relocation Complete

 

$0.00

   Review and Closing of Project

 

$5,100.00

      Finish Payments for Previous Office

Project Manager

$1,200.00

      Advance Payment to New Office Space Owner

Project Manager, Additional Costs[1]

$2,700.00

      Review the Overall Office

Project Manager

$1,200.00

      Milestone 4: Sign Off

 

$0.00

 

 

Stakeholder Identification

The main stakeholders required for the project are as follows.

Stakeholder Name

Stakeholder Designation

Mrs. Devina Clark

Sponsor

Mr. <PLEASE FILL YOUR NAME>

Project Manager

Mr. Martin Rogers

Manager of Supervision and Project Administration

Mr. William Watkins

Manager of Communications and Information Technology (CIT)

Team Operating Principles

The project team will have to abide by the following operating principles.

  • The team will have to cooperate with each other throughout the course of the project.
  • The team will have to exhibit professional behaviour throughout the course of the project.
  • Any issues faced during project must be immediately reported to Manager of Supervision and Project Administration.

Lessons Learned

From the development of this project charter, a lot of knowledge has been gained regarding the planning for a project. It has given insight on determining scope, schedule and budget for a project as well as prepare the plan so as it to avoid the risks and constraints associated.

Charter Closing and Signatures

Stakeholder Name

Signatures

Mrs. Devina Clark

 

Mr. <PLEASE FILL YOUR NAME>

 

Mr. Martin Rogers

 

Mr. William Watkins

 

 

 

References

Conforto, E.C., Salum, F., Amaral, D.C., Da Silva, S.L. and De Almeida, L.F.M., 2014. Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), pp.21-34.

Crawford, J.K., 2014. Project management maturity model. Auerbach Publications.

Flyvbjerg, B., 2014. Megaproject planning and management: Essential readings (Vol. 2). Edward Elgar Publishing.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Routledge.

Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), pp.169-179.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Sharp, J.A., Peters, J. and Howard, K., 2017. The management of a student research project. Routledge.

Špundak, M., 2014. Mixed agile/traditional project management methodology–reality or illusion?. Procedia-Social and Behavioral Sciences, 119, pp.939-948.

Place your order
(550 words)

Approximate price: $22

Homework help cost calculator

600 words
We'll send you the complete homework by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 customer support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • 4 hour deadline
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 300 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more
× How can I help you?